Under deck concrete repairs, Concrete repair, including steel reinforcement treatment Covers concrete chipping and cleaning, rust removal, clearing of reinforcement bars, protection of exposed bars against corrosion, surface filling and leveling with approved low shrinkage structural mortar, Protective coating Covers application of corrosion inhibiting impregnation coating, and application of waterproofing and protective slurry mortar, Front beam concrete repairs, vertical outer part, Transverse beam outer end Covers concrete chipping, concrete cleaning, dust removal, drilling and fixing of four HA-14 steel dowels with epoxy mortar, providing and placing of two HA-8 steel stirrups, brushing and cleaning of steel bars, installing formwork and filling the space with approved low shrinkage structural mortar, Steel piles splash areas.

SCOPE OF WORK
PROJECT DETAILS
Categories: | |
Client: | Dubai Port World |
Location: | Djibouti |
Completed: | On-Going |
Value: | 2,690,000.00 USD |